🚧 Marina Revitalization
-
West Basin is now complete and fully open. It features 1,115 upgraded berths with new enclosed concrete floating docks, ADA‑compliant gangways, in‑slip pump‑outs, better lighting, keyless entry, updated utilities, and a projected lifespan of 70 years Dana Point Harbor Revitalization
-
Phase 7.1 (east portion of E‑dock) is in demolition and reconstruction and is slated to reopen in July 2025, which will wrap up the West Basin redevelopment Phase 7.1
-
Phase 9, covering the East Basin (including Docks M and N and the commercial fishing dock), is set to begin construction in July 2025. The full marina revitalization is on pace for completion by end of 2027 Phase 9
🏗️ Commercial Core & Landside Construction
-
A new three‑level parking structure next to Golden Lantern and Dana Point Harbor Drive (984 stalls, EV charging, restrooms, showers, boater amenities) is approaching completion, expected to open late May or early June 2025 Dana Point Parking Structure
-
Phases 1 and 2 of the landside redevelopment—utility upgrades, pedestrian connections, early retail/restaurant construction—are wrapping up in summer 2025. Phase 3, focusing on waterfront improvements and Wharf buildings, will launch by July/August 2025
-
Plans include 12 revamped or new multi‑tenant commercial buildings, a proposed food hall called Boathouse, green spaces, rooftop decks, public art installations, and event venues. The boardwalk will more than double in length, linking Doheny State Beach to Baby Beach, creating one of the largest walkable harbors on the West Coast OCGOV Info
🏨 Hotels & Planning Updates
-
Two new hotels (one four‑star, one three‑star affordable) replacing the Dana Point Marina Inn have had their draft Environmental Impact Report (EIR) circulated. Public comment closed in late April 2025; the forthcoming Planning Commission hearing is scheduled for June 23, 2025
-
Coastal Commission approved hotel development in June 2024, which included a community benefits package worth over $6 million for service organizations in Orange County
⚓ Community, Programs & Other Components
-
The Dana Point Fisheries Enhancement Program (DPFEP) is planning a relocation to accommodate Phase 9 activities, with options being evaluated and formats to be finalized before construction begins.
-
Upgrades at the OC Sailing & Events Center (OCSEC) include new docks, remodeled Cove Room roof, new skylights, bottle filling stations, and lighting—major improvements to be implemented throughout 2025–2026.
-
Plans are underway to give sea lions designated viewing docks/platforms, allowing them to coexist with harbor activities—intended to reduce wildlife conflict and preserve the harbor's ecological character.
📅 Timeline Overview
Component | Current / Next Milestone | Estimated Completion |
---|---|---|
West Basin marina | Fully complete | Completed by April 2025 |
Phase 7.1 (E‑dock) | Demolition and reconstruction underway | Reopen July 2025 |
Phase 9 (East Basin) | Demolition starting July 2025 | East Basin done by 2027 |
Parking structure | Final inspections, opening imminent | Late May–June 2025 |
Commercial Core Phase 3 | Waterfront & Wharf redevelopment | Starts summer 2025 |
Hotel EIR & approvals | Planning Commission scheduled | June 23, 2025 |
OCSEC upgrades | Implementation through 2025–2026 | By late 2026 |
Overall harbor project | Completion of all phases | Late 2027 |
✅ Summary
Dana Point Harbor’s revitalization is well underway. The West Basin is complete, and focus is shifting to the East Basin and the new commercial core. With the parking garage nearly done, hotel planning progressing, and public amenities expanding, the harbor is set for a full transformation by late 2027. Throughout, public access is being maintained, community input is ongoing, and phased occupancy is allowing continued operation of existing businesses and attractions. OC Parks